Yacht Club Road Drainage and Paving

 

Project Implementation
Completed: May 15, 2019
Jun 30, 2020
Pothole Repair
Completed: Jul 15, 2019
Jul 15, 2019
RFP 2019-05 Asphalt-Yacht Club Road Edisto Beach
Completed: Aug 22, 2019
Jul 29 2019
Bid Award
Completed: Sep 12, 2019
Sep 12 2019
Notice of Award
Completed: Sep 13, 2019
Sep 13 2019
Notice to Proceed
Completed: Sep 23, 2019
Sep 23 2019
Begin Construction
Completed: Oct 15, 2019
Oct 7 2019
Project Completion
Completed: Oct 18, 2019
Oct 21 2019

The end of Yacht Club Road pavement and bike path are in disrepair.  There is also a drainage system that was impacted from the previous years storms.  Town staff will be working on the drainage and the pot holes on Yacht Club Road.  Bids are being acquired for repaving the end of the road as well as the bike path.  

 

Bob Doub, Project Manager

Action Services, Inc.-$36,937

Project Updates

Project Completion
Friday, October 18, 2019

This project was completed on October 18, 2019

Project Start
Tuesday, October 15, 2019

Action Services started the project on October 15, 2019

Notice to Proceed
Monday, September 23, 2019

The business license was obtained and notice to proceed was issued on September 23, 2019.  Robert Doub is overseeing the project for the Town. 

Contract Execution
Thursday, September 19, 2019

The signed contract was received with all backup. 

Notice to Award
Friday, September 13, 2019

Notice to award was mailed on September 13, 2019 with the contract. 

Project Award
Thursday, September 12, 2019

Council awarded the contract to Action Services, Inc. at a cost of $36,937 to be funded from a transfer from general fund contingency to general fund capital projects. 

Pages