Fire Hydrant Maintenance

 

Hydrant Blasting
Completed: Jun 24, 2019
Jun 22 2019
Hydrant Painting
Completed: Jul 12, 2019
Jul 08 2019

The past years of flooding has caused many of our hydrants to show signs of rust.  The Town is in the process of having many hydrants hydroblasted and repainted.  Cool Blast Equipment Company is removing the rust by blasting it with dry ice and the Fire Department will be painting the hydrants.  The project cost is $12,950.00

Phase I of this project has been completed.  Phase II will consist of blasting and painting 20 more hydrants. 

Cool Blast Equipment Company

Project Updates

Hydrant Blasting
Saturday, June 22, 2019

Hydroblasting

Hydrant Maintenance
Saturday, June 22, 2019

Hydrant Ready to Paint