Emergency Operations Center/Town Hall

 

Funding
Completed: Jun 13, 2019
Jun 13 2019
Issue RFQ
Completed: Oct 31, 2019
Oct 31 2019
Pre Proposal Meeting
Completed: Dec 16, 2020
Dec 16 2019
Receive Proposals
Completed: Jan 21, 2020
Jan 21 2020
Review Proposals
Completed: Feb 24, 2020
Feb 24 2020
Presentations from Short Listed Firms
Completed: Apr 28, 2020
Mar 25, 2020
Council Award Contract
Completed: May 14, 2020
May 14 2020
Notice of Award
Completed: May 15, 2020
May 15 2020
2nd Notice of Award
Completed: Aug 13, 2020
August 13, 2020
Series of Meetings on Design
Completed: Oct 31, 2021
Oct 31 2021
Final Building Design
Completed: Nov 30, 2021
Nov 30 2021
Submit Proposal for CPST Funding
Completed: Jan 24, 2022
Jan 24 2022
CPST Commission Formed by Colleton County
Completed: Apr 6, 2021
Apr 6 2021
CPST Commission Ranked Projects
Completed: May 11, 2022
May 11 2022
Colleton County approved Ordinance 22-O-08
Completed: Jul 26, 2022
Jul 26 2022
Referendum
Nov 08 2022
Advertise for Bids
Sept 2024
Award Construction Contract
Nov 2024
Permitting Complete
Jan 2025
Contractor NTP
Jan 2025
Substantial Completion
Feb 2026

Town Hall is located at 2414 Murray Street.  The current Town Hall was built in 1985 on a 0.26 acre site (Lots 9 & 10 Block UU).  It is a one story building and began as 2,491 square feet and was renovated in 2005 by Charleston Constructors for $148,000 and is now 3,042 SF.   The construction is wood frame on a concrete slab (elevation 11.90'MSL) with brick and vinyl exterior walls.   

The Fire Department was built in 1986.  It is a 4,990 SF metal building at a slab elevation of 12.21' MSL.  Most of this building is used for  fire engine parking. The Police Department and Municipal Court are also housed in this building. 

The retention building for storage of permanent records is 421 SF.  

In 2015, the Town purchased 2412 Murray Street for $96,500 for parking. 

Thirty three years later,  the Town has 38 employees housed in a space constructed when there were 8-10 employees.  The  Police Department needs an evidence room, interrogation room, bathroom and shower facilities as well as space for officers.   The municipal court needs an area separate from the Police Department. The Town needs an Emergency Operations Center.  The Town is housing some staff at the civic center,  but they are unable to connect to the Town's server because Internet is unreliable.  It is not efficient to house staff in different areas especially outside of its jurisdiction.  

In 2014, Colleton County voters passed a referendum to implement a 1 cent sales tax to meet infrastructure needs in Colleton County. The Town applied for and was successful in obtaining $4,000,000 for beach nourishment during that cycle.  The 1 cents sales tax cycle is 8 years.  The next cycle will begin 2021. 

The Town budgeted funds ($50,000) to hire an architect to design a Town Hall Complex and establish a cost so we can submit an application for a new Town Hall Complex in the next 1 cent sales tax cycle.  The complex would be constructed on the same site as Town Hall is now, but it would be brought up to the current codes and be elevated.   The Town does not plan to borrow funds for this project.  If we are unsuccessful in obtaining the 1 cent sales tax, the understanding is the project will not move forward. 

 

 

 

Project Manager-Mark Aakhus

Committee-Mayor Moore, Councilman Kizer, Mark Aakhus, Chief Denney Conley, Chief Daniel Seyle, Patrick Brown, Patrick Zemp

Firm-Rosenblum Coe

$50,000

Town Hall Complex Design Committee

Mayor Crawford Moore

Councilman Jerome Kizer

Edye Graves

Katherine Kuntz

Mark Aakhus, Assistant Town Administrator

Patrick Brown, Building Codes Administrator

Documents

Project No. 2019-10 Documents
Rosenblum Coe Contract
Project No. 2019-10 Documents
Design Presentation
Amendment #1
Amendment #1 $6,908
Town Hall Complex Concept
Town Hall Complex Concept
Estimated Cost Construction April 21, 2021
Estimated Cost of Construction April 21, 2021
Preliminary Design-8/31/2021
Preliminary Design August 31 2021
Conceptual Design Costs
Conceptual Design Costs September 23, 2021

Project Updates

Town Hall Design Committee Meeting
Thursday, April 22, 2021

The Town Hall Design Committee met to review the draft plans and estimated construction costs from April 21, 2021. The following notes were sent to the architect to be addressed 

Notes

  • Everyone seemed to really like the general look, design and layout of the buildings.
  • General materials: metal roof, hardie board siding, masonry-type siding on bottom, horizontal wood louver design, storefront windows
  • Does the cost estimation include site work (grading, site utilities, parking lot paving, landscaping, etc.)?
  • Provide temporary office accommodations cost estimate on a monthly rental/square footage basis.
  • Are there any additional project costs not listed, other than contingency?
  • What is the general layout for entering the Town Hall Lobby (stairs and elevator only)?
  • Can you provide an option for the Town Hall entrance with an exterior staircase.
  • Will there need to be a retention pond on the site?  Location?
  • D-2 Seismic considerations?
  • Will everything be sprinklered?
  • What are the “inherently higher” fire department costs?  Commercial kitchen with suppression requirements?
  • Payment windows need to be consolidated and located at building entrance.
  • General floor plan should feel open.
  • Town Hall to have a section of office with glassed offices on perimeter with multipurpose work stations in the middle (similar to Kiawah Town Hall design)
  • Discussion of housing the Chamber of Commerce in shared lobby space.
Town Hall Complex Design Committee Formed
Tuesday, January 26, 2021

During the annual Council retreat, Council formed a committee to provide input on the complex design.

Kick-off Meeting
Wednesday, September 16, 2020

Meeting was held with Department Heads to determine space needs for the proposed new facility.

Council Award
Thursday, August 13, 2020

The Town failed to negotiate terms of the contract with the initial firm and withdrew award and Council awarded to second highest ranked firm. 

Council Award
Thursday, May 14, 2020

Council approved award to the selected firm. 

Project Update
Friday, May 1, 2020

Presentations from short listed firms were made to the selection committee virtually on April 27 and 28.  The selection committee recommendation will be presented to Council May 14, 2020. 

Pages